Mirboo North Outdoor Pool Redevelopment

The redevelopment of the Mirboo North pool is a large capital works project that will secure the future of a community asset that has been used and loved by local residents since 1904. It is expected that the new facility will be able to meet the needs of the community for another 50 plus years.

A total of $5.73 million has been allocated to the project. In an amazing effort, the Mirboo North Community raised $1 million to support the project. The Federal Government contributed $600,000 and the Victorian Government $190,000. Council will fund the remaining project cost.

mn pool

Progress Report - August 2021

  • Main 25 metre and Learn-To-Swim pools are complete and filled with water
  • Pool Plant room is complete, pool plant services and equipment are in the final stages of commissioning.
  • Gereral landscaping works are nearing completion (awaiting a spell of fine weather to complete).
  • Pavilion building complete (awaiting final clean).
  • Stage 1 Carpark works are under way. Asphalt, line-marking and bollards are expected to be completed by mid August 2021.
  • Handover imminent (August 2021).